Question: QUESTION 8 A project is scheduled to be completed within 1 6 months and the total cost of the project is 1 0 0 ,

QUESTION 8
A project is scheduled to be completed within 16 months and the total cost of the project is 100,000 USD. Eight months have passed, and 55,000 USD has been spent. After a closer review, you (as a project leader) found that only 40% of the work has been completed so far, while 50% of work was expected. Complete the following?
Note: [Earned Value =% of completed work (Planned Total Project Cost
 QUESTION 8 A project is scheduled to be completed within 16

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!