Question: QUESTION 8 A project is scheduled to be completed within 1 6 months and the total cost of the project is 1 0 0 ,
QUESTION
A project is scheduled to be completed within months and the total cost of the project is USD. Eight months have passed, and USD has been spent. After a closer review, you as a project leader found that only of the work has been completed so far, while of work was expected. Complete the following?
Note: Earned Value of completed work Planned Total Project Cost