Question: QUESTION 8 You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0 A. The
QUESTION 8
- You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0
A. The project's deliverables have all been finished. The project came in ahead of schedule (before due date)but on budget.
B. The project's deliverables are not all finished. The project came in behind schedule(after due date)but on budget.
C. The project's deliverables have all been finished. The project came in on schedule but over budget.
D. The project has been canceled while it was executed. At that time the project was behind schedule and on budget.
Incorrect- The project's deliverables have all been finished. The project came in on schedule but over budget.
QUESTION 10
- You are the project manager of for a software (App) development project. Your company's management has recently decided to get the ISO 9001 certification. As a result, you now need to make sure that your project complies and adhere to the additional requirements. The first step for an ISO 9001 certification will be:
A. A company prepares several documents that report its internal processes, procedures and standards.
B. Ensuring that your organization maps its processes to a proven process methodologyfollowing a benchmark company.
C. Creating a fixed path for the entire company to follow strictly, without any deviations.
D. Ensuring that your project used both quality plan, quality assurance, quality control, and integrates them within the project.
Incorrect- Ensuring that your organization maps its processes to a proven process methodology following a benchmark company.
QUESTION 11
- As a project lead, your team is on its way to finishing work on the project, while you have the impression that a staff member is already negotiating the next assignment in another project. You are afraid that the person may come under pressure to start working on the other job before she has finished her work for your project. Her task is very complex, and it would be hard for someone else to take up the partial results and finish them. What action is most likely to resolve the situation?
A. Have a private meeting with the person and discuss your observations. Make the person aware of the contract and of the legal consequences of unfinished work.
B. Use your network of project managers to find another assignment for the person which allows for smooth transition and does not conflict with your needs.
C. Have a meeting with the entire team and discuss the person's expected early leave. Use team dynamics to buy in the commitment from the person to finish work orderly.
D. Ignore your observations and let the team member do her job. It is quite uncommon that staff drops work for a project before it is completely finished.
Incorrect- Have a private meeting with the person and discuss your observations. Make the person aware of the contract and of the legal consequences of unfinished work.
QUESTION 18
- You are responsible to manage a large internal project in a Consultancy company. To staff this project, you contacted Skill-net Consultancy to provide five computer code specialist for one year. The resources will be part of the team managed by Yam Consultancy for six months. Which contract type should be used by Yam Consultancy?
A. Purchase Order
B. Fixed cost
C. Time and Material
D. Cost plus Fee
Incorrect- Time and Material
QUESTION 19
- You found the following earned value analysis information for a project that was recently closed-out: SPI = 1.0, CPI =1.2
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget
B. The project's deliverables have all been finished. The project came in on schedule but under budget, which is the best result.
C. The project's deliverables have all been finished. The project came in behind schedule but on budget
D. The project's deliverables have all been finished. The project came in behind schedule but on budget.
Incorrect- The project has been cancelled while it was executed. At that time the project was behind schedule and on budget