Question: Question (89) a) Perform a forward pass and backward pass through the network to determine the critical path , the expected duration of the project

Question (89)

a) Perform a forward pass and backward pass through the network to determine the critical path, the expected duration of the project, and the slack time for each activity.

b) What is the probability that the project will be completed one week or more before the expected completion time?

c) What is the probability that the project will be completed two weeks or more before the expected completion time?

Question (89) a) Perform a forward pass and

a) Perform a forward pass and backward pass through the network to determine the critical path, the expected duration of the project, and the slack time for each activity. (50 points) b) What is the probability that the project will be completed one week or more before the expected completion time? Also, compare the value you found against the value stated for the previous table (i.e., the respective value provided in the solution set of the HW-3 problem) (30 points) c) What is the probability that the project will be completed two weeks or more before the expected completion time? (20 points) Most likely time (weeks) Pessimistic time (weeks) Immediate predecessor Activity Optimistic time (weeks) A 2 B 3 4 3 3 4 4 5 m + D D 6 8 A 2 4 1 3 6 B B,C E 5 9 5 7 G 6 8 9 10 4 DE E H 2 3 00 m 00 4 8 12 E J 3 3 4 5 F 3 6 9 G H 1,J L 2 4 6 M 1 2 3 K, L

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!