Question: Question 9 ( 1 point ) The sum of activity durations of the longest path in a network indicates expected project completion time, and the

Question 9(1 point)
The sum of activity durations of the longest path in a network indicates expected
project completion time, and the activities on it are called the c ritical activities.
True or false
 Question 9(1 point) The sum of activity durations of the longest