Question: Question 9 ( 1 point ) The sum of activity durations of the longest path in a network indicates expected project completion time, and the
Question point
The sum of activity durations of the longest path in a network indicates expected
project completion time, and the activities on it are called the c ritical activities.
True or false
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock