Question: Time left 1 : 2 5 : 1 7 The sum of activity durations of the longest path in a network indicates expected project completion

Time left 1:25:17
The sum of activity durations of the longest path in a network indicates expected project completion time, and the activities on it are called the critical activities.
Select one:
True
False
The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.