Question: Question 9 15 pts For an item requiring a Master Production Schedule, the following information is available: 12 4 40 0 Week 1 3 5

Question 9 15 pts For an item requiring a Master
Question 9 15 pts For an item requiring a Master Production Schedule, the following information is available: 12 4 40 0 Week 1 3 5 Forecast 30 30 30 30 Booked Orders 42 24 16 0 The Week Ooh-hand inventory for this item is 62 units. This item has a 1 week lead time. This item's hot-size policy is that it must be ordered in foed quantities of 35, and there are no safety stock requirements. In which weeks should orders of this item arrive? Weeks 3 and 5 Weeks 2 and 4 Weeks 1.2 and 4 Weeks 2.3 and 5