Question: Question 9 3 pts Below is a data for a project. (in months) In the 3rd week of this project, it was determined that activity

Question 9 3 pts Below is a data for a project.

Question 9 3 pts Below is a data for a project. (in months) In the 3rd week of this project, it was determined that activity E will have a duration of 2 months. With this change, what is the minimum amount months will it take to complete the entire project? activity duration (months) predecessor A 1 B 5 A 8 A D 3 E 1 6 B, C 2 D, E G H 4 F G