Question: Question 14 3 pts Below is data for a project. (in months) In the 3rd week of this project, it was determined that activity B

Question 14 3 pts Below is data for a project.

Question 14 3 pts Below is data for a project. (in months) In the 3rd week of this project, it was determined that activity B will have a duration of 10 months. With this change, how many more months will it take to complete the entire project? Hint: What is the change (delta) between the amount of months to complete in each scenario. activity duration (months) predecessor A 1 -- 1 5 B 5 8 A D 3 3 A E 1 C F 6 B, C G 2 DE H 4 F G