Question: Question 9 5 pts A PERT network was constructed for the release of a new automobile technology. Expected activity times and variances are shown below.

Question 9 5 pts A PERT network was constructed

Question 9 5 pts A PERT network was constructed for the release of a new automobile technology. Expected activity times and variances are shown below. Activity Expected Time Variance A 10 3 B 4 2 7 5 D 3 3 E 8 1 The critical path is A-C-E. The expected duration of the project is and the standard deviation of project time is