Question: Question 9 Contract documentation includes but is not limited to Select one: a. Requested and approved contract changes b. All of these answers are correct
Question 9 Contract documentation includes but is not limited to Select one: a. Requested and approved contract changes b. All of these answers are correct c. Payment records d. Seller performance reports e. The contract
2
For an FPIF contract:
Target cost = 100,000
Target fee = 50,000
Target price = 150,000
Sharing ratio: 60% buyer, 40% seller
Ceiling price = 175,000
Actual cost = 140,000
(Enter your answer below rounded to a whole number with no commas.)
The point of total assumption (PTA) =