Question: QUESTION 9 Event Management is a system to manage A. Remote surgical treatment system B. Any event such as a birthday of important persons in
QUESTION 9
Event Management is a system to manage
A. Remote surgical treatment system
B. Any event such as a birthday of important persons in the hospital
C. is a broadening of the computerized physician order entry system
D. admission order for surgery triggers a series of follow-up events such as booking OR, surgical team, recovery room etc.
E. C and D
QUESTION 11
In an MRP problem, A is an MPS item. Every A requires 3 B's and 2 C's. Every B requires 5 C's. All lead times are one period. Initial inventory values for all items are 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned order release for C in period 8?
a. 800
b. 1600
c. 6800
d. 6000
e. 1200
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts