Question: question 9: What is the expected project duration before crashing any activities? question 10: What is the cost of the third crash? question 11: What

question 9: What is the expected project duration before crashing any activities?
question 10: What is the cost of the third crash?
question 11: What is the cost of the sixth crash?
question 12: What is the total cost of all crashes that should be done to minimize costs?
question 13: How much should be spent on penalties?
Use this info for questions 9 through 13. Chuck's Custom Boats (CCB) builds customer luxury yachts. CCB has landed a contract with a mysterious New York real estate developer, Mr. T. Relevant data on the project are shown below. The complication is that Mr. T wants delivery in 30 weeks or he will impose a penalty of $250 for each week his yacht is late. Determine the lowest cost plan for crashing this project. Note: All numbers are in thousands, but keep them that way (i.e., don't enter the last three zeros). What is the expected project duration before crashing any activities? Crash Cost Activity Immediate Predecessor Normal Time (weeks) # Possible Crashes Per Week - 10 175 = . 45 . 60 3 v 20 z 55 MN 265 o 70
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
