Question: QUESTION 9 You are the project manager for a construction project. Your sponsor has asked you for a forecast for the cost of project completion.
You are the project manager for a construction project Your sponsor has asked you for a forecast for the cost of project completion. The projoct has a bodal budget of 5160.000 and a Cont Pertormance index (CPI) of 0.5 . The project has spent 525,000 of is budget so far. Calculate the Estimate bo Complete (ETC) for this project? 175,0005130,0005200,000550,0005