Question: You are the project manager for a construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project

You are the project manager for a construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $100,000 and a Cost Performance Index (CPI) of 0.5. The project has spent $25,000 of its budget so far. Calculate the Estimate to Complete (ETC) for this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock