Question: Question 90: Price analysis does not have to be done on: (a) Contracts under $600,000 (b) Micropurchases (c) Simplified acquisition (d) Competitive proposals (e) None

Question 90: Price analysis does not have to be done on:

(a) Contracts under $600,000

(b) Micropurchases

(c) Simplified acquisition

(d) Competitive proposals

(e) None of the above

Question 97: The performance-based statement of work:

(a) Does not include positive and/or negative performance incentives

(b) Should include application of only selected aspects of the total PBSC

methodology

(c) Must define work in completion terms

(d) None of the above

Question 100: __________ statement of work is the preferred method of stating needs.

(a) Design/detail

(b) Level-of-effort

(c) Performance-based

(d) None of the above

Question 102: Performance specifications should contain requirements that have the

characteristics of being:

(a) Quantitative rather than qualitative

(b) Verifiable

(c) Material and process independent

(d) All of the above

Question 103: In more complex source selections, the plan for selecting a best value source is

called the:

(a) Source Selection Plan

(b) Technical Evaluation Plan

(c) Acquisition Plan

(d) None of the above

Question 104: In most cases the __________ is the selection official.

(a) Contracting officer

(b) Agency head

(c) Program Manager

(d) None of the above

Question 105: Which of the following should be provided for in standard internal procedures

established for proposal preparation?

(a) The quality of the reproduction and binding

(b) A list of illustrations needed

(c) The development of the initial proposal plan and outline

(d) All of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!