Question: Question a) Complete a Gantt Chart using the data from Table. Indicate on the chart the early start dates, durations and associated float for each

Question a) Complete a Gantt Chart using the data
Question a) Complete a Gantt Chart using the data from Table. Indicate on the chart the early start dates, durations and associated float for each task. Early Start Employees Activity Succeeding tasks Float (days) Duration (Days) (Day) Required (Per Day) A 9 0 B,C,D 1 4 12 E,F B 4 6 EF C D E F G H I Resource Table LL E,F GH H HH I I . 0 0 0 1 0 1 0 0 4 6 6 7 80 10 3222 2 2 1 2 2 2 1 3 6 9 15 52 12 9