Question: Question Completion Status: Consider the following AOA network with the following activity times: A-15, B=12, C=14, D=16, E=12, F=15, G=14, H=13, 1=15 D B H

Question Completion Status: Consider the

Question Completion Status: Consider the following AOA network with the following activity times: A-15, B=12, C=14, D=16, E=12, F=15, G=14, H=13, 1=15 D B H E dummy 0 0 G I A F What is the slack time for activity H? 3 01 4 02 2