Question: Question: Consider a construction project with the following activities, their immediate predecessors, and estimated durations ( in days ) : table [ [ Activity
Question: Consider a construction project with the following activities, their immediate predecessors, and estimated durations in days:
tableActivityPredecessors,tableDurationdaysABACADAEBCFBGGDHFIEFJHI,
a Draw the network diagram using PDM for the project.
points
b Calculate the project duration. point
c Find all the project' paths and identify the Critical Path.
points
d Determine the Total Float for each activity.
points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
