Question: Question: Consider a construction project with the following activities, their immediate predecessors, and estimated durations ( in days ) : table [ [ Activity

Question: Consider a construction project with the following activities, their immediate predecessors, and estimated durations (in days):
\table[[Activity,Predecessors,\table[[Duration],[(days)]]],[A,-,4],[B,A,2],[C,A,4],[D,A,5],[E,B,C,3],[F,B,G,8],[G,D,2],[H,F,5],[I,E,F,2],[J,H,I,1]]
a. Draw the network diagram using PDM for the project.
(4 points)
b. Calculate the project duration. (1 point)
c. Find all the project' paths and identify the Critical Path.
(3 points)
d. Determine the Total Float for each activity.
(2 points)
 Question: Consider a construction project with the following activities, their immediate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!