Question: Question content area Part 1 In a project network, non - critical activities that have little slack need to be monitored closely because A .

Question content area
Part 1
In a project network, non-critical activities that have little slack need to be monitored closely because
A.
slack is undesirable and needs to be eliminated
B.
near-critical paths could become critical paths with small delays in these activities
C.
they have a high risk of not being completed
D.
they are causing the entire project to be delayed
E.
PERT/CPM treats all activities as equally important