In a project network, noncritical activities that have little slack need to be monitored closely because
A
slack is undesirable and needs to be eliminated
B
nearcritical paths could become critical paths with small delays in these activities
C
they have a high risk of not being completed
D
they are causing the entire project to be delayed
E
PERTCPM treats all activities as equally important