Question: Question content area Part 1 Marsek company is developing a program in supply chain management certification for managers. Marsek has listed a number of activities

Question content area
Part 1
Marsek company is developing a program in supply chain management certification for managers. Marsek has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity
Immediate Predecessor(s)
Time(days)
A
minus
10
B
minus
7
C
minus
1
D
B
2
E
A, D
3
F
C
5
G
E, F
12
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
.
c) The project length for the leadership training program development project=
enter your response here days.
d) Slack time for each of the activities is:
Activity
Slack Time
A
enter your response here
B
enter your response here
C
enter your response here
D
enter your response here
E
enter your response here
F
enter your response here
G
enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!