Marsek company is developing a program in supply chain management certification for managers. Marsek has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity
Immediate Predecessors
Timedays
A
minus
B
minus
C
minus
D
B
E
A D
F
C
G
E F
This exercise contains only parts b c and d
b The critical activities for the leadership training program development project are
c The project length for the leadership training program development project
enter your response here days.
d Slack time for each of the activities is:
Activity
Slack Time
A
enter your response here
B
enter your response here
C
enter your response here
D
enter your response here
E
enter your response here
F
enter your response here
G
enter your response here
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock