Question: Question content area Part 1 In the following table the activities with their precedence sequence and expected time ( days ) are listed for a
Question content area
Part
In the following table the activities with their precedence sequence and expected timedays are listed for a project on which Carl Betterton's construction company is working:
Activity
Immediate Predecessors
Timedays
A
minus
B
A
C
A
D
B
E
B
F
C
G
D
H
E F
Part
Carls team should be able to complete the project in
days.
Part
Critical path activities for Carl's project are
A C F H
A B E H
A C F H
A B D G