Question: Question content area Part 1 Scheduling techniques that load ( or assign ) work only up to the capacity of the process are called Part
Question content area
Part
Scheduling techniques that loador assign work only up to the capacity of the process are called
Part
A
demand loading.
B
infinite loading.
C
finite loading.
D
capacity loading.