Question: Question content area Part 1 Which is the best statement regarding work breakdown structure? Part 2 A . A packet is the smallest unit of
Question content area
Part
Which is the best statement regarding work breakdown structure?
Part
A
A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
B
WBS should not include a task representing planning of the project that is being planned.
C
Each activity in the WBS must have an "owner" who is responsible for doing the work.
D
A Level activity is a more micro viewgreater level of detail than a Level activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
