Question: Question content area Part 1 Which is the best statement regarding work breakdown structure? Part 2 A . A packet is the smallest unit of

Question content area
Part 1
Which is the best statement regarding work breakdown structure?
Part 2
A.
A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
B.
WBS should not include a task representing planning of the project that is being planned.
C.
Each activity in the WBS must have an "owner" who is responsible for doing the work.
D.
A Level 1 activity is a more micro view(greater level of detail) than a Level 2 activity.