Question: Which is the best statement regarding work breakdown structure? Part 2 A . A Level 1 activity is a more micro view ( greater level
Which is the best statement regarding work breakdown structure?
Part
A
A Level activity is a more micro viewgreater level of detail than a Level activity.
B
A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control.
C
Each activity in the WBS must have an "owner" who is responsible for doing the work.
D
WBS should not include a task representing planning of the project that is being planned.