Question: QUESTION FOUR [25] The data gathered {optimistic (a); most probable (m) and pessimistic (b) times} for a project you are managing are listed in the
QUESTION FOUR [25]
The data gathered {optimistic (a); most probable (m) and pessimistic (b) times} for a project you are managing are listed in the table below:
ActivityPredecessorMost
Optimistic (a)
Most
Probable(m)
Most
Pessimistic (b)
DaysA-7812B-369C-4711DA;B81216EB;C567FD91316GE6813HF;G4914IH356
- Using the PERT formula, calculate the time and the variance for each activity. (5)
- Construct the network (AON) and identify the critical path (12)
- Calculate the probability of this project finishing within: (8)
- 48 days
- 50 days