Question: QUESTION FOUR [25] The data gathered {optimistic (a); most probable (m) and pessimistic (b) times} for a project you are managing are listed in the

QUESTION FOUR [25]

The data gathered {optimistic (a); most probable (m) and pessimistic (b) times} for a project you are managing are listed in the table below:

ActivityPredecessor

Most

Optimistic (a)

Most

Probable(m)

Most

Pessimistic (b)

DaysA-7812B-369C-4711DA;B81216EB;C567FD91316GE6813HF;G4914IH356

  1. Using the PERT formula, calculate the time and the variance for each activity. (5)
  2. Construct the network (AON) and identify the critical path (12)
  3. Calculate the probability of this project finishing within: (8)
    • 48 days
    • 50 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!