Question: Question list Question 8 Question 9 The demand for subassembly S is 1 1 0 units in week 7 . Each unit of S requires

Question list
Question 8
Question 9
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V,2 units of W, and 2 units of x. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,1 week to make V,3 weeks to make W,1 week to make x,2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Construct a gross material requirements plan (type 0 if the input box is not used).
\table[[Item,,Week,\table[[Lead Time],[(weeks)]]],[,1,2,3,4,5,6,7],[s,Gross req,,,,,,,,],[Order release,,,,,,,11,2],[\table[[T,]],Gross req,,,,,,,,],[Order release,,,,,,,,1],[U,Gross req,,,,,,,,],[Order release,,,,,,,,2],[v,Gross req,,,,,,,,],[Order release,,,,,,,,1],[w,Gross req,,,,,,,,],[Order release,,,,,,,,3],[x,Gross req,,,,,,,,],[Order release,,,,,,,,1],[Y,Gross req,,,,,,,,],[Order release,,,,,,,,2],[z,Gross req,,,,,,,,],[Order release,,,,,,,,1]]
 Question list Question 8 Question 9 The demand for subassembly S

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!