Question: Question (make a graphical AON with providing the legend) Develop a List of 12 Milestones with associated Predecessors and Duration for a project you can

Question (make a graphical AON with providing the legend)

Develop a List of 12 Milestones with associated Predecessors and Duration for a project you can think of. (you may use examples from our Breakout room projects). Use the following 4 headings: ID, Description, Predecessor, and Time Duration. When developing your list and assigning predecessors, ensure there are at least 3 bursts and 4 merges in the project you are creating to allow you to demonstrate your understanding of the AON Diagram methodology.

ID Description Predecessor(s) Time Duration

ID

DESCRIPTION

PREDECESSOR(S)

DURATION

1

Market Research

None

2 Months

2

Product Design

1

3 Months

3

Prototype Development

2

5 Months

4

Product Testing

3

2 Months

5

Production Planning

4

1 Months

6

Manufacturing

5

9 Months

7

Quality Control

6

1 Months

8

Product Launch

7

1 Months

9

Marketing Campaign

8

2 Months

10

Product Evaluation

9

1 Months

11

Customer Feedback Analysis

10

1 Months

12

Improvement and Upgrades

11

2 Months.

Note : be sure to include a legend for your network.

And please make a graphical AON diagram.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!