Question: Question (make a graphical AON with providing the legend) Develop a List of 12 Milestones with associated Predecessors and Duration for a project you can
Question (make a graphical AON with providing the legend)
Develop a List of 12 Milestones with associated Predecessors and Duration for a project you can think of. (you may use examples from our Breakout room projects). Use the following 4 headings: ID, Description, Predecessor, and Time Duration. When developing your list and assigning predecessors, ensure there are at least 3 bursts and 4 merges in the project you are creating to allow you to demonstrate your understanding of the AON Diagram methodology.
ID Description Predecessor(s) Time Duration
| ID | DESCRIPTION | PREDECESSOR(S) | DURATION |
| 1 | Market Research | None | 2 Months |
| 2 | Product Design | 1 | 3 Months |
| 3 | Prototype Development | 2 | 5 Months |
| 4 | Product Testing | 3 | 2 Months |
| 5 | Production Planning | 4 | 1 Months |
| 6 | Manufacturing | 5 | 9 Months |
| 7 | Quality Control | 6 | 1 Months |
| 8 | Product Launch | 7 | 1 Months |
| 9 | Marketing Campaign | 8 | 2 Months |
| 10 | Product Evaluation | 9 | 1 Months |
| 11 | Customer Feedback Analysis | 10 | 1 Months |
| 12 | Improvement and Upgrades | 11 | 2 Months. |
Note : be sure to include a legend for your network.
And please make a graphical AON diagram.