Question: Question - math Answer A and B 2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate total throughput
Question - math
Answer A and B

2. Determine the processing sequence for the six jobs shown below using Johnson's Rule. (A) Calculate total throughput (makespan) time. (12 pts) (B) Can the makespan be reduced by splitting the latest job? If so, by how much? (8 pts) Working Job Working Center 1 Center 2 a 4 6 b a 8 C 10 5 P 16. e 11 a a f 9 7