Question: Question No: 06 nuvaly UICELL VALUL Predecessor - (weeks) 8 8 12 A B D E F G H I J K A A A


Question No: 06 nuvaly UICELL VALUL Predecessor - (weeks) 8 8 12 A B D E F G H I J K A A A B E, C E, D F F G H I, J WONA 6 2 6 2 a. Draw a neat network diagram b. What is the ES, EF, LS, LF dates, and slack of each activity? c. Draw a neat Gantt chart for LS/LF schedule d. Explain in detail the importance of slack in managing a project