Question: Question one: A job is divided into four work elements. Work element t F RF 1 0.4 1 1 2 0.32 0.5 0.8 3 0.2
Question one:
A job is divided into four work elements.
Work element
t
F
RF
1
0.4
1
1
2
0.32
0.5
0.8
3
0.2
1
1.2
4
0.5
1
1.3
Calculate the normal time. Assuming that the allowance is 20 percent of the normal time. Calculate the standard time for this job. What are the uses of the calculated standard time for managers?
Question Two:
A companys learning rate is 90 percent. The first unit of product takes 1,500 hours to produce. Estimate how many hours would be required to complete the 55th unit. Also, draw the learning curve.


Question A job is divided into four work elements Work cment + 1 04 1 1 0.32 0.5 0.B a 0.2 1 12 05 1 13 Calculate the normal time. Auming that the wlowance is 20 percent of the normal time. Calculate the standard time for this job. What are the war of the calculated standard time for managers? Question Two A company's leaming rate is so percent. The first unit of product takes 1.500 hours to produce Estimate how many hours would be required to complete the 55th unit. Ako, draw the leaming curve FI . . Abdivided to our workers Work de 04.1 om as a 02112 0.5 13 Calore the normal tine. coming that the allowance is 20 percent of the normal tine. Calabate the danced sine for this. What are the res of the calculated anded time for more! Quran A company's leaning rate is 00 percent. The trunk at products 1,900 hours to produceras how many hours would be required to complete the hunt. Al rew thing are W WPS Office o A
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
