Question: Question: right arrow Based on standard CPM node notation - which statement is TRUE about task R shown below? ( numbers shown are in days
Question: right arrow Based on standard CPM node notation which statement is TRUE about task R shown below? numbers shown are in days
A
The earliest day task R can start is day
B
It will take days to complete task R
C
The slack time for task R is days
D
The earliest finish for task R should actually be day
E
Task R is on the critical path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock