Question: Question: right arrow Based on standard CPM node notation - which statement is TRUE about task R shown below? ( numbers shown are in days

Question: right arrow Based on standard CPM node notation- which statement is TRUE about task R shown below? (numbers shown are in days)
A.
The earliest day task R can start is day 8
B.
It will take 8 days to complete task R
C.
The slack time for task R is 5 days
D.
The earliest finish for task R should actually be day 9
E.
Task R is on the critical path