Question: hich statement is true about Project Management? A . Slack is defined as the difference between the earliest start and the latest finish of a

hich statement is true about Project Management?
A. Slack is defined as the difference between the earliest start and the latest finish
of a task
B. The critical path has slack time of zero for all activities
C. Project crashing is an effort to maximize project duration
D. The earliest finish for a task is equal to the latest start plus the task duration
E. None of the above statements are true
2. If your earliest start is 8 and your latest start is 10 for the same activity in a CPM
(Critical Path Method) analysis, which of the following statement holds?
A. The earliest finish time must be 8 B. The slack for this activity is 2
C. The latest finish time must be 12 D. All of the above
E. None of the above
3. Flow time (not the theoretical flow time) can be defined as:
I. The time that a unit is being processed by the machines and workers in the system
II. The time that a unit which leaves the process has spent within the process
III.The time for a unit to move through the system
2
A. I B. I and II only C. II and III only
D. I and III only E. I, II and III
4. The advantage(s) of the network planning models such as CPM diagram over the Gantt
chart is (are) that:
A. It is easy to use and quite widely understood
B. The precedence relationships in network scheduling are explicitly shown
C. They are less costly to use
D. Both A and B E. Both B and C
5. In this 4-week cycle, what is the average inventory?
Week Input rate Output rate
1600400
2600750
3600500
4600550
A.50 B.100 C.150 D.200 E. None of the above
6. In Toyotas Georgetown Kentucky plant, one finished car rolls off the assembly line
every 20 seconds. It takes 100 minutes to assemble a car. How many cars are being
worked on in the assembly line at any given point in time?
A.100 cars B.200 cars C.300 cars D.400 cars
E.500 cars
3
7. Which of the following statement is NOT true regarding operations frontier?
A. d is more desirable than e but less desirable than b
B. There is a trade-off for firm to operate at a or c, but both are equally desirable
C. Ensuring firm to operate at the operations frontier is a strategic issue
D. It is possible for firm e to operate at b through process improvement
E. Firm a is equally desirable as b
8. Please find the inventory level at the end of 5-weeks production based on the following
table. The starting inventory at the beginning of week 1 is 100.
Week Input Rate Output Rate
1200300
2300100
3400200
4200600
5300200
A.0 units B.100 units C.200 units D.300 units E. None of the above
9. Following the above question, assume that inventory changes in discrete steps weekly.
What is the average inventory level for the 5-week period?
A.40 units B.140 units C.180 units D.200 units E. None of the above
Quality
4
10. Based on the following network with activity durations, the critical path is:
A. A-B-E-G B. A-C-F-G C. A-D-F-G D. None of the above
11. Following the above question, the activity times (in weeks) and costs (in dollars) are
given as follows. To reduce the project time to 17 weeks in a most cost effectively,
which activities should to be crashed:
Activities Normal
Time
Normal
Cost
Crash
Time
Crash
Cost
Crash
Cost/week
A 23001450150
B 64804960240
C 114009620110
D 103007900200
E 86006960180
F 52403600180
G 34203420--
A. A, C and F only B. A, C and E only C. A, C, E and F
D. A, C, D and E. E. None of the above
12. Which of the following is not a typical type of process?
A. Job Shop B. Batch C. Commodity Flow
D. Project E. Assembly Line
5
13.________ is when the activities in the stage must stop because there is no work.
A. Buffering B. Blocking C. Starving
D. Setup E. None of the above
14. The following table shows the unit load of processing product A and product B for
each resource. What is the bottleneck resource for the product mix of 2A+1B?
Unit load (min/unit)
Product A Product B
Resource 154
Resource 208
Resource 363
A. Resource 1 B. Resource 2 C. Resource 3
D. Resource 1 and 3 E. Unknown
15. The Children Hospital has 200 beds for patients. On average, the hospital beds have
a 90% occupancy rate. Suppose the average length of stay is 3 days. On average,
how many patients are discharged from the hospital on any given day?
A.120; B.90; C.60; D.30; E. None of the above
16. Consider a process consisting of two activities with different unit loads shown
below (s for second):
To double the output per hour, you can
A. Buy one more Machine 1 for Activity 1(working in parallel)
B. Replace Machine 2 with a faster machine which cuts the unit load by half
C. Buy one more Machine 2 for Activity 2(working in parallel)
D. Both B and C; E. None of the above
17. You are the manager of a project. Today, you observe your cumulative cost chart
and find that BCWC (budgeted cost for work completed) is right now above BCWS
(budgeted cost for work scheduled). W

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!