Question: Question: Set-up the constraints that will be required to create an optimal production schedule. Assume actual sales are same as demand values. A similar question

Question: Set-up the constraints that will be required to create an optimal production schedule. Assume actual sales are same as demand values.

A similar question was answered on CHEGG here: https://www.chegg.com/homework-help/questions-and-answers/question-set-constraints-required-create-optimal-production-schedule-assume-actual-sales-d-q59983975?trackid=p7XRlnOH

and here: https://www.chegg.com/homework-help/Supply-Chain-Management-6th-edition-chapter-9-problem-2E-solution-9780133800203

Overtime, hiring, layoffs, are allowed. Backordering and SUBcontracted are NOT allowed; That is, there must be enough inventory in each month to supply that month's expected demand. In Period 12, the ending inventory must be 5000 units.

YOU ARE NOT REQUIRED TO USE EXCEL-SOLVER. Just provide the constraints for any of the following variables given the information below:

Costs
Regular Time Labor 15
Overtime Labor 22
Inventory carrying cost (per unit per month) 3
Material cost (per unit) 40
Selling Price (per unit) 125
Hiring Cost (per new employee) 1000
Lay-off cost (per laid off employee) 2000
Starting Inventory 5000
Desired Ending Inventory 5000
Overtime Limit (number of units produced per employee) 10
Production Capacity (per employee per month) 80 units
Starting Workforce 250 workers
Labour hours per unit 2
MAX overtime per month per employee, HOURS 20
# of working days per month 20
# of hours per day 8

DEMAND

10000

11000
16000
19000
22000
25000
31000
28000
22000
19000
13000
12000

Question: Set-up the constraints that will be

A F G H K M 1 B C D E # of employees Ht (#Hire Lt (# Laid off) Wt (Workforce) Ot (Overtime) 250 In Units C# Subcontracted) Pt (Production) Demand Max OT Available Production Capacity Actual Sales 2 PERIOD 3 0 (Starting) It (Inventory) 5000 4 1 0 10000 5 2 0 10000 11000 16000 6 6 3 0 7 4. 0 19000 11000 16000 19000 22000 25000 8 5 0 9 9 6 0 10 7 0 31000 11 8 0 0 22000 25000 31000 28000 22000 19000 13000 12 9 0 13 10 0 28000 22000 19000 13000 12000 14 11 0 15 12 0 12000 ANY CONSTRAINTS? Workforce Ot (Overtime) It (Inventory) Inventory OT_Overtime et (Sebeontracteet) Pt (Production) Actual Sales 0 N/A 0 0 0 0 0 0 16 17 Related Costs 18 Period Ht (#HiredLt (# Laid off) Wt (Workforce) 19 1 20 2 21 3 22 4 23 5 24 6 25 7 26 8 27 9 28 10 29 11 30 12 31 Total over all periods 32 33 Total Cost 34 Total Revenue 35 Total Profit 0 0 0 0 0 A F G H K M 1 B C D E # of employees Ht (#Hire Lt (# Laid off) Wt (Workforce) Ot (Overtime) 250 In Units C# Subcontracted) Pt (Production) Demand Max OT Available Production Capacity Actual Sales 2 PERIOD 3 0 (Starting) It (Inventory) 5000 4 1 0 10000 5 2 0 10000 11000 16000 6 6 3 0 7 4. 0 19000 11000 16000 19000 22000 25000 8 5 0 9 9 6 0 10 7 0 31000 11 8 0 0 22000 25000 31000 28000 22000 19000 13000 12 9 0 13 10 0 28000 22000 19000 13000 12000 14 11 0 15 12 0 12000 ANY CONSTRAINTS? Workforce Ot (Overtime) It (Inventory) Inventory OT_Overtime et (Sebeontracteet) Pt (Production) Actual Sales 0 N/A 0 0 0 0 0 0 16 17 Related Costs 18 Period Ht (#HiredLt (# Laid off) Wt (Workforce) 19 1 20 2 21 3 22 4 23 5 24 6 25 7 26 8 27 9 28 10 29 11 30 12 31 Total over all periods 32 33 Total Cost 34 Total Revenue 35 Total Profit 0 0 0 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!