Question: Question Six Suppose you are working on a new software product development. Table below provides the information about the activities, immediate predecessors, normal time and
Question Six
Suppose you are working on a new software product development. Table below provides the information about the activities, immediate predecessors, normal time and costs and crash times and costs.
tableActivitytableImmediatePredecessorstableNormalTimeweekstableCrashTimeweekstableNormalCost$tableCrashCost$ANone,BNone,CABDBECDFCGE F
i Draw an Activity on Arrow AoA diagram for the project activities
marks
ii Determine the critical path of the project
marks
iii. If management wanted to reduce the project period to weeks to beat competition, which activities can they crash? Illustrate your answer with a crash table and total crash cost.
marks
iv Calculate the planned crash cost of the project
marks
v Draw a full Gant chart for the resulting project showing activity, Precedence and optimized duration.
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock