Question: Question Six Suppose you are working on a new software product development. Table below provides the information about the activities, immediate predecessors, normal time and

Question Six
Suppose you are working on a new software product development. Table below provides the
information about the activities, immediate predecessors, normal time and costs and crash times
and costs.
i. Draw an Activity on Arrow (AOA) diagram for the project activities
ii. Determine the critical path of the project
iii. If management wanted to reduce the project period to 20 weeks to beat competition, which
activities can they crash? (Illustrate your answer with a crash table and total crash cost.)
iv. Calculate the planned crash cost of the project
v. Draw a full Gant chart for the resulting project showing activity, Precedence and optimized
duration.
(10 marks)
 Question Six Suppose you are working on a new software product

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!