Question: Question: The Hard Rock Concert Case Student Instructions Each year the Hard Rock organizes a huge concert called the Rock Fest. Some 100 000 rock
Question:
The Hard Rock Concert Case
Student Instructions
Each year the Hard Rock organizes a huge concert called the "Rock Fest." Some 100 000 rock and roll fans attend the Rock Fest. Planning for the concert begins many months before the actual concert date. This year the concert will take place on the Saturday of Labour Day weekend, Sept. 3rd,2022. Planning for the concert begins on Feb. 1st,2022. As a recent operations management graduate, you have been hired to help schedule this year's concert. Hard Rock follows a normal workweek and observes all traditional Canadian holidays. Specifically, these holidays include Good Friday (April 15th), Easter Monday (April 18th); Victoria Day (May 23rd ), July 1st. All planning activities must be complete by Sept. 2nd, 2022)
Below is a table detailing the specific activities associated with staging Rock Fest. Included in the table are precedence activities, the normal amount of time and normal amount of cost associated with each task, as well as the number of days an activity can be shortened to and its total cost to crash to that time.
For this case you are to:
1) Draw the network. You may use Microsoft Project. Indicate ES, EF, LS, LF times.
3) Identify all pathways and completion times. Identify the critical pathway.
4) Print the Slack Table for your initial diagram.
5) Now, crash this project so that the concert can take place as planned (Sept. 3rd). Identify the tasks you will shorten to achieve this goal and adjust the durations of these activities so that the "finish time" indicates the concert can take place as scheduled.
6) Print a new Network Diagram showing the new critical path. This will be your "After" Network Diagram.
7) Print a new Slack Table.
8) What is the Total Cost of putting on this concert and how much Extra did you have to spend to get the concert on schedule?
Hard Rock Concert
| Normal Time | Normal Time | Task can be | Total Cost of | |||
| Activity | Description | Predecessors | In Days | Cost | Shortened to | Shortened Time |
| A | Finalize sites & facility contracts | 28 | $10 000 | |||
| B | Select Concert Promoter | A | 14 | $7500 | ||
| C | Hire Production Manager | B | 21 | $5000 | ||
| D | Design Promotional Website | B | 24 | $15 000 | ||
| E | Finalize TV rights | B | 59 | $8000 | 51 | $1 000/day |
| F | Hire Director | B | 28 | $7500 | ||
| G | Plan for TV camera placement | F | 13 | $7250 | ||
| H | Target headline entertainers | B | 45 | $12 500 | 43 | $2 500/day |
| I | Target support entertainers | H | 43 | $11 000 | ||
| J | Travel accommodations for talent | I | 4 | $6000 | 3 | $660/day |
| K | Set venue capacity | C | 3 | $2000 | ||
| L | Sign Ticket Master contract | B, D, K | 16 | $6000 | ||
| M | On-site ticketing | L | 6 | $1500 | 4 | $2000/day |
| N | Lease sound and staging equipment | C | 8 | $5500 | ||
| O | Passes & stage credentials | G, R, P | 4 | $2500 | 2 | $1500/day |
| P | Travel accommodations for staff | U, W | 4 | $4000 |
| Normal Time | Normal Time | Task can be | Total Cost of | |||
| Activity | Description | Predecessors | In Days | Cost | Shortened to | Shortened Time |
| Q | Hire Sponsor Coordinator | B | 21 | $5900 | 20 | $250/day |
| R | Finalize sponsors | Q | 35 | $9000 | 32 | $1500/day |
| S | Define & place signage for sponsors | Q, E, X | 8 | $3000 | 31 | $500/day |
| T | Sign concession contracts | B, K | 32 | $8000 | ||
| U | Hire Operations Manager | B | 48 | $5500 | 43 | $3300/day |
| V | Develop site plan | U | 31 | $9000 | 27 | $1200/day |
| W | Hire Security Director | B | 20 | $4200 | ||
| X | Hire Support Staff | U, W | 17 | $3600 | ||
| Y | Develop police/fire security plan | W | 55 | $10 000 | 50 | $1 000/day |
| Z | Develop traffic plan | W, M, J, T | 20 | $9500 | 18 | $750/day |
| AA | Determine reqmt's for power, facilities | V | 30 | $6200 | 26 | $800/day |
| BB | Secure merchandise deals | B | 25 | $6100 | 22 | $500/day |
| CC | Secure online merchandise sales | BB | 20 | $4700 | 18 | $700/day |
| DD | Install power/ plumbing/ AC/toilet svcs | AA | 6 | $9500 | 5 | $300/day |
| EE | Construct stage | C, N, V, AA, DD | 2 | $8000 | ||
| FF | Test sound/lighting | O, DD, EE | 2 | $3000 | 1 | $1500/day |
| GG | Ready for concert | Y, Z, CC, S, FF | 1 |