The information in Table 1 relating to a multi-national vaccine trial for Covid-19 refers.
| Activity | Duration (Weeks) | Predecessor |
| A | 5 | - |
| B | 6 | A |
| C | 7 | A |
| D | 10 | A |
| E | 10 | B,C |
| F | 8 | C,D |
| G | 12 | D |
| H | 2 | E,F |
| I | 15 | F |
| J | 10 | F,G |
Table 1 - Dependency table for the Covid-19 vaccine trial project
Based on the information in Table 1, draw the network diagram on a separate piece of paper by completing the forward and backward passes.
With reference to your network diagram, answer the following questions:
- Using the network diagram that you have drawn, what is the slack for activity H?
- What is the Late Startfor activity C?
- What is the Critical Path?
- What do activities B, C, D & E, F, G as well as H,I, Jhave in common?
- What is the Late Finishfor activity G?
- What would the impacton the project be if the slackfor activity C was used?