QUESTION THREE [25]
The information relating to a project that you are working on is listed in the table below:
Activity Predecessor Optimistic
Time
(Days)
Most likely
Time
(Days)
Pessimistic
Time
(Days)
A -4824
B -31011
C -61224
D A;B 91425
E B;C 111627
F D;E 131535
G F 5919
Required:
3.1 Using the PERT formula calculate the time value (t) for each activity and construct
the network diagram (Activity on Node).(10)
3.2 Calculate the Early Start; Late Start; Early Finish & Late Finish and slack times for
all activities. (10)
3.3 Identify the paths and show critical path. (5)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!