Question: QUESTION THREE [ 2 5 ] The information relating to a project that you are working on is listed in the table below: Activity Predecessor
QUESTION THREE
The information relating to a project that you are working on is listed in the table below:
Activity Predecessor Optimistic
Time
Days
Most likely
Time
Days
Pessimistic
Time
Days
A
B
C
D A;B
E B;C
F D;E
G F
Required:
Using the PERT formula calculate the time value t for each activity and construct
the network diagram Activity on Node
Calculate the Early Start; Late Start; Early Finish & Late Finish and slack times for
all activities.
Identify the paths and show critical path.