Question: QUESTION [25 marks] The information relating to a project that you are working on is listed in the table below: Activity Predecessor Optimistic Times (Days)
QUESTION [25 marks]
The information relating to a project that you are working on is listed in the table below:
| Activity | Predecessor | Optimistic Times (Days) | Most likely Time (Days) | Pessimistic Time (Days) |
| A | - | 4 | 8 | 24 |
| B | - | 3 | 10 | 11 |
| C | - | 6 | 12 | 24 |
| D | A:B | 9 | 14 | 25 |
| E | B:C | 11 | 16 | 27 |
| F | D:E | 13 | 15 | 35 |
| G | F | 5 | 9 | 19 |
Required:
3.1 Using the PERT formula calculate the time value (t) for each activity and construct the network diagram (Activity on Node). (10 amrks).
3.2 Calculate the Early Start; Late Start; Early Finish & Late Finish and slack times for all activities. (10 marks)
3.3 Identify the paths and show critical path. (5 marks )