Question: QUESTION THREE [ 2 5 ] The information relating to a project that you are working on is listed in the table below: table

QUESTION THREE
[25]
The information relating to a project that you are working on is listed in the table below:
\table[[Activity,Predecessor,\table[[Optimistic],[Time],[(Days)]],\table[[Most likely],[Time],[(Days)]],\table[[Pessimistic],[Time],[(Days)]]],[A,-,4,8,24],[B,-,3,10,11],[C,-,6,12,24],[D,A;B,9,14,25],[E,B;C,11,16,27],[G,F,5,9,15]]
Required:
3.1 Using the PERT formula calculate the time value (t) for each activity and construct the network diagram (Activity on Node).
3.2 Calculate the Early Start; Late Start; Early Finish & Late Finish and slack times for all activities.
(10)
3.3 Identify the paths and show critical path.
(5)
 QUESTION THREE [25] The information relating to a project that you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!