Question: QUESTION THREE [ 2 5 ] The information relating to a project that you are working on is listed in the table below: table
QUESTION THREE
The information relating to a project that you are working on is listed in the table below:
tableActivityPredecessor,tableOptimisticTimeDaystableMost likelyTimeDaystablePessimisticTimeDaysABCDA;BEB;CGF
Required:
Using the PERT formula calculate the time value t for each activity and construct the network diagram Activity on Node
Calculate the Early Start; Late Start; Early Finish & Late Finish and slack times for all activities.
Identify the paths and show critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
