Question: Question Two (15 Marks): Given the following network, compute the early start and finish, late start and finish, and slack time for each activity. Clearly

Question Two (15 Marks): Given the following
Question Two (15 Marks): Given the following network, compute the early start and finish, late start and finish, and slack time for each activity. Clearly identify the critical path. Lag 1 D 3 7 Lag 5 E F B 3 Lag 3 2 1 2 Lag 1 Lag 4 Lag 4 G