Question: QUESTION TWO: (20 MARKS) Use the following project data to answer questions below. (Time is given in weeks). ACTIVITY PREDECESSOR OPTIMISTIC TIME MOSTLIKELY TIME PESSIMISTIC
QUESTION TWO: (20 MARKS)
- Use the following project data to answer questions below. (Time is given in weeks).
| ACTIVITY | PREDECESSOR | OPTIMISTIC TIME | MOSTLIKELY TIME | PESSIMISTIC TIME |
| 1 | - | 2 | 4 | 8 |
| 2 | - | 1 | 2 | 3 |
| 3 | 1,2 | 3 | 5 | 8 |
| 4 | 3 | 2 | 2 | 3 |
| 5 | 1,2 | 3 | 4 | 7 |
| 6 | 4,5 | 4 | 6 | 9 |
| 7 | 6 | 8 | 12 | 20 |
| 8 | 7 | 2 | 3 | 5 |
| 9 | 7 | 2 | 2 | 3 |
| 10 | 8 | 5 | 8 | 12 |
| 11 | 8 | 6 | 9 | 14 |
| 12 | 9,10 | 3 | 4 | 7 |
| 13 | 11,12 | 3 | 4 | 6 |
| 14 | 11 | 2 | 3 | 5 |
| 15 | 14 | 4 | 6 | 9 |
| 16 | 13 | 2 | 2 | 3 |
- The project completion time, critical activities and all paths for the project Network. (8 marks)
- The likelihood of completing the project in 60 weeks. (6 marks)
- Discuss the responsibilities of a Project Support office. (6 marks)