Question: QUESTION TWO: (20 MARKS) Use the following project data to answer questions below. (Time is given in weeks). ACTIVITY PREDECESSOR OPTIMISTIC TIME MOSTLIKELY TIME PESSIMISTIC

QUESTION TWO: (20 MARKS)

  1. Use the following project data to answer questions below. (Time is given in weeks).

ACTIVITY

PREDECESSOR

OPTIMISTIC TIME

MOSTLIKELY TIME

PESSIMISTIC TIME

1

-

2

4

8

2

-

1

2

3

3

1,2

3

5

8

4

3

2

2

3

5

1,2

3

4

7

6

4,5

4

6

9

7

6

8

12

20

8

7

2

3

5

9

7

2

2

3

10

8

5

8

12

11

8

6

9

14

12

9,10

3

4

7

13

11,12

3

4

6

14

11

2

3

5

15

14

4

6

9

16

13

2

2

3

  1. The project completion time, critical activities and all paths for the project Network. (8 marks)
  2. The likelihood of completing the project in 60 weeks. (6 marks)

  1. Discuss the responsibilities of a Project Support office. (6 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!