Question: Use the following problem statement to answer questions 1-6. BK Home, a homebuilding company, plans to build a new shopping center. A consultant for the

 Use the following problem statement to answer questions 1-6. BK Home,
a homebuilding company, plans to build a new shopping center. A consultant
for the company has constructed a project network and estimated activity times,

Use the following problem statement to answer questions 1-6. BK Home, a homebuilding company, plans to build a new shopping center. A consultant for the company has constructed a project network and estimated activity times, in weeks. The consultant found the following critical path: ACD. The expected activity times of A,C and D are 10,5, and 5 weeks. The variances of A,C and D are 3,1 , and 2 . Round to four decimal places. [Note: z=(X t)/, where X= given value; t= expected project completion time; = standard deviation of the project completion time] APHEUS Standard Normal Distribution Table The table entries represent the are under the standard normal curve from 0 to the specified value of z. What is the expected project completion time? B 4 20 What is the probability the project can be completed in more than 22 weeks? 80.42%20.61% Question 3 4 pts What is the standardized z-value for the value of 22 ? Use the expected project completion time and the standard deviation of the project completion time. 0.81654.32643.3368 Question 4 4 pts What is the probability the project can be completed within 22 weeks? 13.61%79.39%32.46% What is the standard deviation of the project completion time? 1.0000 2.4495 Question 6 4pts What is the variance of the project completion time? 1 Use the following problem statement to answer questions 1-6. BK Home, a homebuilding company, plans to build a new shopping center. A consultant for the company has constructed a project network and estimated activity times, in weeks. The consultant found the following critical path: ACD. The expected activity times of A,C and D are 10,5, and 5 weeks. The variances of A,C and D are 3,1 , and 2 . Round to four decimal places. [Note: z=(X t)/, where X= given value; t= expected project completion time; = standard deviation of the project completion time] APHEUS Standard Normal Distribution Table The table entries represent the are under the standard normal curve from 0 to the specified value of z. What is the expected project completion time? B 4 20 What is the probability the project can be completed in more than 22 weeks? 80.42%20.61% Question 3 4 pts What is the standardized z-value for the value of 22 ? Use the expected project completion time and the standard deviation of the project completion time. 0.81654.32643.3368 Question 4 4 pts What is the probability the project can be completed within 22 weeks? 13.61%79.39%32.46% What is the standard deviation of the project completion time? 1.0000 2.4495 Question 6 4pts What is the variance of the project completion time? 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!