Question: QUESTION TWO [ 3 0 ] The estimated times for a project that you are working on is listed in the table below: ACTIVITY PREDECESSOR

QUESTION TWO [30]
The estimated times for a project that you are working on is listed in the table below:
ACTIVITY PREDECESSOR MOST OPTIMISTIC
(DAYS)
MOST LIKELY
(DAYS)
MOST PESSIMISTIC
(DAYS)
A -6916
B A 111520
C A 2610
D B 101215
E B 256
F C 4612
G E;F 6914
H D;E 3711
I H;G 369
2.1 Using the PERT formula, calculate the time (t) value for each activity. Please round
off days i.e. no decimal places. (5)
2.2 Calculate the variance (v) for each activity. Please use 2 decimal places. (5)
2.3 Construct the network diagram (Activity on Node AON).(15)
2.4 Calculate the probability of this project being completed in 55 days. (5)
Answer requires a page count: six (6) pages maximum.V

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!