Question: Question Two: A project manager is tasked with estimating the duration of three critical tasks in a construction project: foundation laying, building structure, and interior

Question Two:
A project manager is tasked with estimating the duration of three critical tasks in a construction project: foundation laying, building structure, and interior finishing. The manager gathers input from relevant stakeholders and obtains the following estimates for each task:
Foundation Laying:
Optimistic Time (O): 5 days
Most Likely Time (M): 8 days
Pessimistic Time (P): 12 days
Building Structure:
Optimistic Time (O): 10 days
Most Likely Time (M): 15 days
Pessimistic Time (P): 20 days
Interior Finishing:
Optimistic Time (O): 7 days
Most Likely Time (M): 10 days
Pessimistic Time (P): 14 days
Using the Program Evaluation and Review Technique (PERT), calculate the expected duration and standard deviation for each task.
 Question Two: A project manager is tasked with estimating the duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!