Question: QUESTION TWO Given the information on table 1, Using the AoN notation, Draw a complete network diagram, showing early start times, late start times and
QUESTION TWO
- Given the information on table 1, Using the AoN notation,
- Draw a complete network diagram, showing early start times, late start times and floats for each of the listed activities. [14 marks]
- What is the shortest period that the project (depicted by network diagram) will take to complete? (Ignoring all other compounding factors) [6 marks]
| Table 1: Activity schedule for Project ALFONSO | ||
| Activity | Predecessor | Expected Duration (weeks) |
| A | - | 6 |
| B | A | 7 |
| C | A | 5 |
| D | B | 3 |
| E | C | 4 |
| F | C | 5 |
| G | D,E | 8 |
| H | F,G | 3 |