Question: QUESTION TWO Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in
QUESTION TWO
Using the information in the table below, assuming that the project team will work a standard working week working days in week and that all tasks will start as soon as possible:
tableTaskDescription,tableDurationWorking DaysPredecessorsARequirement Analysis,BSystems Design,ACProgramming,BDTelecoms,BEHardware Installation,BFIntegration,C DGSystem Testing,E FHDocumentation,GITrainingSupportHJHandover and GoLive,HKMaintenance,I, J
Determine the critical path of the project.
Calculate the planned duration of the project in weeks.
Identify any noncritical tasks and the float free slack on each.