Question: QUESTION TWO Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in

QUESTION TWO
Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:
\table[[Task,Description,\table[[Duration],[(Working Days)]],Predecessor/s],[A,Requirement Analysis,4,-],[B,Systems Design,12,A],[C,Programming,20,B],[D,Telecoms,6,B],[E,Hardware Installation,23,B],[F,Integration,7,C, D],[G,System Testing,13,E, F],[H,Documentation,2,G],[I,Training/Support,5,H],[J,Handover and Go-Live,3,H],[K,Maintenance,3,I, J]]
2.1 Determine the critical path of the project.
(8)
2.2 Calculate the planned duration of the project in weeks.
(4)
2.3 Identify any non-critical tasks and the float (free slack) on each.
(3)
 QUESTION TWO Using the information in the table below, assuming that

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!