Question: Question 4 Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1

Question 4

Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:

Task DescriptionDuration (Working Days)Predecessor/sARequirement Analysis4-BSystems Design12ACProgramming20BDTelecoms6BEHardware Installation23BFIntegration7C, DGSystem Testing13E, FHDocumentation2GITraining/Support5HJHandover and Go-Live3HKMaintenance3I,J

4.1 Determine the critical path of the project. (6 marks)

4.2 Calculate the planned duration of the project in weeks. (6 marks)

4.3 Identify any non-critical tasks and the float (free slack) on each. (8 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!