Question: Question type: Critical Path Method The activities described by the following table are given for the Howard Corporation in Kansas: table [ [ Activity
Question type: Critical Path Method
The activities described by the following table are given for the Howard Corporation in Kansas:
tableActivityImmediate Predecessor,Time,,,ABCADAEBCFBGDEHF
a Draw the appropriate AON Network diagram with all ES EF LS LF and slack for JC Howard's management team. Or build a table with all ES EF LS LF
b Find the critical path.
c What is the project completion time?