Question: Question type: Critical Path Method The activities described by the following table are given for the Howard Corporation in Kansas: Activity Immediate Predecessor Time A
| Question type: Critical Path Method | ||||
| The activities described by the following table are | ||||
| given for the Howard Corporation in Kansas: | ||||
| Activity | Immediate Predecessor | Time | ||
| A | - | 7 | ||
| B | A | 9 | ||
| C | A | 3 | ||
| D | B | 6 | ||
| E | B | 9 | ||
| F | C | 4 | ||
| G | E,F | 6 | ||
| H | D | 5 | ||
| I | G,H | 3 | ||
| a) Draw the appropriate AON PERT diagram for J.C. Howards | ||||
| management team. | ||||
| b) Find the critical path. | ||||
| c) What is the project completion time? | ||||
please show formulas you use to get the answers
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock